Filed under: Miscellaneous
It has been a very busy week on the field of dreams project and the leadership team has been pushed to the max. Particularly project manager Jim Hartley has taken many hours away from his salary paying job to keep FOD going. Removing the concrete debris from the track project took much longer and many more bins than we first thought. The worst part was that it was not part of the original budget. Thankfully the track boosters have offered to make a contribution to cover this cost. A couple of setbacks occured when the newly placed storm drain pipe got damaged and a backflow valve got bumped. Steve Wheeler has come out during the week to operate the trencher so the volunteers can place the irrigation pipe.
Last weekends report-
activity. JRS construction has trenched and placed our storm drain
system. The size of the concrete inlets is very impressive as you see
them lifted into the air and placed. Last Thursday and Friday was very
dusty as the heavy equipment traversed the fields and kicked up dust
into 30 mph winds. There is an access point to a large county sewer line
that requires an extension place to compensate for the raised elevation
of the field hockey field. This work should be finished on Monday and
our volunteer corps will have full access to complete the project in
time for our scheduled planting of turf.
the team. Karl Uhrenholt drove the water tank on a continuous mission to
suppress the dust during the work period. Our most critical path item is
the trenching for the irrigation system. We have a top-of-the-line
trencher provided to us by Doc Pond, a softball parent. Andrew Thompson, Bob Shiner and Jim Elledge provided yeoman duty on the trencher. On Sunday Scott Bruns and the Cheer group did a fantastic job painting the new trench lines to guide the trencher operators. This is another critical item since the trenchers must follow the plan very exactly. Mike White has done so much
to move us forward in the “taking care of problems” department. Using a
skip loader donated by Joe and Gayle Hensler and their team at TEAM POWER, Mike loaded the remaining concrete debris into bins for removal. The bins have been provided at a discount through Mike Strombeck. I think that by now you can understand how so many people have worked to make this all come together.
Toni Fairall and her crew swept the football practice field clean of debris.
We have hired Bert Wickey to grade the football practice area, smooth out the
together. We have hired Gary Vollstedt to teach and supervise our crew of
No Comments so far
Leave a comment
Leave a comment
Line and paragraph breaks automatic, e-mail address never displayed, HTML allowed:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <code> <em> <i> <strike> <strong>

