Football Steps Out with a Donation; Soccer Matches and Raises them $500; Track considers
Saturday September 16th 2006, 5:00 pm
Filed under: Miscellaneous, Athletic Booster Club

Looking to see if other clubs can also contribute, Kathy Smith announced last week that the Football Club will (more…)



Saturday the 16th proves the most effective Volunteer Day yet!
Saturday September 16th 2006, 4:43 pm
Filed under: Miscellaneous

Over thirty volunteers, propelled by the commitment of the softball team - who made this a mandatory work day - completed all the group tasks for the day in (more…)



UPDATE - Lacrosse and Soccer Will Play at BV in Spring ‘07!
Monday September 11th 2006, 10:55 pm
Filed under: Plans and Schematics, Miscellaneous

Tonight the Bella Vista Athletic Booster Club Board voted to raise additional funds to place high quality sod on the new soccer and field hockey/lacrosse fields, thus setting the fields up to be competition-ready for the Spring season. This keeps Boys and Girls Lacrosse and Girls Soccer on campus for the Spring and will provide a more uniform playing surface with less initial maintenance. As importantly, this will be a big step to reducing erosion in winter rains of the newly graded fields. 

As part of this action, the Board elected to secure a credit line to cover the extra expenditures. The project budget now stands at $105,000, less than 5% over the original budget of $100,400 approved by the Board in June. Given the discovery of loads of concrete rubble and of transite pipe requiring removal as a hazardous material, as well as the District-mandated obligation to provide compost for the soil, this near-budget outcome was made possible by a substantial donation of services by AdLand Venture, the landscape contractor who will oversee our grass planting (open areas, practice fields) and sod placement.

 



URGENT Schedule Update
Sunday September 10th 2006, 8:11 pm
Filed under: Volunteers Needed, Miscellaneous

We only have 35 days before our grass has to be planted, and effectively only three more volunteer weekends to do about 5 days worth of work. So… (more…)



Volunteers Clear Debris, Drink Kabbalah
Saturday September 09th 2006, 9:32 pm
Filed under: Miscellaneous

September 9th started our final work days, and 20 volunteers worked hard to clear the debris from the Football Practice field and install the main irrigation line. (more…)